Heineken Wastewater Treatment Plant

Construction of foundations, slabs, and building services to support a new wastewater treatment plant for Heineken's brewery.

SERVICES

Concrete Foundations Piping Electrical

Location

Timaru, South Canterbury

Status

Completed in 2023

Works Description

Project included 195 tonnes of fabricated reinforcing steel and 720m3 of 40Mpa low-shrinkage concrete poured for slabs ranging 200mm-500mm thick. Works also covered 829m of new influent and effluent above-ground pipelines with steel pipe supports, and a full electrical fit out. All works were completed while the brewery remained fully operational.

Concrete Foundations

720m3 of specialised concrete poured for heavy wastewater tanks and support buildings.

Piping Systems

Over 800m of above-ground influent and effluent pipelines installed with steel supports.

Live Environment

Works were successfully planned and completed without disrupting the operational brewery.